Due date for traffic cuts in Imperio St (between streets Ecuador and Costa Rica) are carried out following this schedule.
Mansory works During 12 weeks will be carried out four traffic cuts during one hour.
Installation phase, carpentry works and final works: Duration of 18 months. There will be carried out three traffic cuts 3 hours each, and 10 traffic cuts one hour each to collect material.
Traffic cuts must be carried out in off peak hours, between 9:30 and 14:00 hours or between 16:00 hours and 20:00 hours. Traffic will be closed just as necessary to carry out works reopening road at the end of downloading works. There must be free access to garages in the area. Road can not be closed to traffic if works are not being carried out.
>